Next Generation Infrastructure Solutions
) Profile Markets Services Join Our Team Contact Login



Fishelosophy
Management Team
Strategic Partners
Clients Served/List
Safety Program
Locations
Newsletter
Multimedia Library

Team Fishel Awarded California Segment Of The Asia-America Gateway

The Asia-America Gateway is a $550-million project placing 20,000 kilometers or 12,500-miles of submarine fiber optic cable along the Pacific Ocean floor. Once completed, this network will provide connectivity to the Philippines, Malaysia, Singapore, Thailand, Vietnam, Hong Kong, Hawaii and the US west coast. This particular route was chosen to reduce risk of damage due to natural disasters such as earthquakes, tsunamis and/or volcanic eruptions.

According to Doug Mauk, Chandler Project Manager, the California segment involved four major areas. The first was the construction of the EMT pathways at the AT&T Underground facility. Second was the outside plant removal and placement of approximately 10 ½ miles of fiber optic and power cables. The third segment was the construction of an ocean ground bed, which included 227-feet of boring and placing four anodes. The final segment was the restoration of the Montana de Oro State Park Rim Trail. The initial value of the contract was $265,000 but due to additional work grew to $310,000 for this new customer.

"From the beginning, we were in a race to beat the ship to the beach landing point," says Mauk. "It was coming from Hawaii installing the submarine cable while we were completing the ten-plus mile terrestrial portion."

Mauk and Juan Ochoa, Supervisor from Irvine, jointly managed the project. A total of five crews were assigned to the project working from the central California coastline at Los Osos to San Luis Obispo. Due to the rough, hilly terrain, the crews rented fourwheel drive pickups which could haul the Arnco pulling machines, mini-excavators and loaders to the remote manhole locations. At times, weather conditions such as rain, fog and wind, hampered productivity and more than a few Teammates had a run in with poison oak!

Due to the nature of the work, inspectors from Alcatel-Lucent, (the general contractor) inspectors from BHC Rhodes (the engineering company), archeologists, landowners, coastal commissioners and environmental monitors were on-site throughout the project. Teammates received special environmental training before the project kicked-off due to this area being the habitat of the Morro Shoulderband Snail, an endangered species.

Environmental inspectors preceded the crews on the Rim Trail to ensure that no fish, frogs, snails or other protected species were harmed by our caravan of four-wheel-drive vehicles. The crews followed the environmental impact study requirements and if any violations had occurred, the environmental inspectors had the authority to halt the work.

"This was a great team effort by everyone involved," says Mauk. The project was successfully completed in April.

Corporate Headquarters  |  1366 Dublin Road  |  Columbus, Ohio 43215  |  614-274-8100  |  800-347-4351  |  Copyright 2004-2009
Columbus Fibernet Website