TEAM FISHEL PROVIDES TURNKEY SOLUTIONS AT DAVIS MONTHAN AIR FORCE BASE
Last November, Team Fishel’s
Government Services Division
began a turnkey conduit and
manhole project at the Davis
Monthan Air Force Base in Tucson,
Arizona. This $635,000 project
was awarded to Northrop
Grumman Defense Group as part
of the Network Centric Solutions
(NETCENTS) contract. The Air
Force planned to consolidate base
personnel into newer buildings,
which did not have adequate voice
and data capacity. This project
provided immediate relief to those
targeted locations and reinforced
the substructure for future base
expansion.
According to Jeff Weigandt,
Program Manager, the majority
of work was completed by crews
from Tucson.
“Tucson Foreman Nathan Vance
was assigned to the project as
co-lead for the outside plant phase,”
said Weigandt. “Nathan is the type
of person you can brief in the
morning and have full confidence
in his ability to keep things
coordinated and moving forward.”
Weigandt also utilized two backhoe
crews from Phoenix and a
directional drilling crew from
Chandler to complete 17 drill
shots. In all, the job consisted of
15 manholes and approximately
10,000 feet of conduit structure.
Once the conduit system was
complete, copper and fiber cables
were installed and terminated
in the central office, which
required the build-out of the main
distribution frame.Weigandt called
on technicians from Phoenix to
perform the inside plant work,
splicing and testing cables.
The crews encountered
numerous abandoned gas,
water and sewer lines as
well as buried building
foundations and structures,
which were
left in place during base
renovations in the 1940’s
and 50’s. There were
several fiber owners on the
base such as PrevenTronics,
which installed fiber for
security cameras, Qwest,
Base Communications,
the Federal Aviation Administration, and Flight Line
Operations, which owns the control
tower communications. Weigandt
had several meetings in the field as
unmarked fibers were exposed so
the government could try to
decipher who owned them.
“If it wasn’t for the skill of our
Backhoe Operators, we would have
caused severe damage to many of
the lines that were unmarked,” said
Weigandt.
Even with all of the unmarked
lines they encountered, Fishel
Teammates did not cause any
service outages, which Weigandt
contributes to a little bit of luck and
a lot of Operator skill.
“This project was full of obstacles
from day one,” said Bill Pauley,
Vice President of Western Region.
“But experience and knowing the
government’s internal protocol
allowed Team Fishel to keep
working. Jeff Weigandt clearly
demonstrated Team Fishel PRIDE
which may lead to future
opportunities at Davis Monthan.”
|